Ducon Infratechnologies Limited (Formerly Known As Ducon Technologies (I) Private Limited) v. Elecon Engineering Company Ltd.
928-ARBP208-20-I.DOC Druti
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 208 OF 2020 Ducon Infratechnologies Limited, (Formely known as Ducon Technologies (I) Pvt. Ltd.
...Petitioner
Versus
Elecon Engineering Company Ltd
...Respondent
Ms Bharati Narichania, i/b Vibha Jurisconsult, for the Petitioner. Ms Shilpa Kapil, with Ms Snehal More & Ms Tajashree Kank, for the Respondent.
CORAM:
G.S. PATEL, J.
DATED:
13th February 2020 PC:- 1.
The petition is under Section 29-A of the Arbitration and Conciliation Act 1996. Disputes arose between the parties under an agreement entered between them. By an order dated 27th July 2018, an advocate of this Court was appointed as the Sole Arbitrator. The Arbitrator entered upon the reference to his arbitration shortly thereafter and the matter proceeded before him. 2.
The original arbitral mandate was extended by mutual consent. The extended arbitral mandate ended on 29th January 13th February 2020
928-ARBP208-20-I.DOC 2020. The arbitral proceedings have reached the stage of cross examination of Petitioner's witnesses.
3.
Having regard to these circumstances, I am extending the arbitral mandate from 29th January 2020 until 31st December 2020 to complete the arbitral proceedings.
4.
The petition is disposed of accordingly.
(G. S. PATEL, J) 13th February 2020