Babaji Shivram Clearing And Carriers Pvt. Ltd. v. Bharat Heavy Electricals Limited

2020-02-13Hon'Ble Shri Justice G.S. Patel2 pages

933-CARBPL130-20-I.DOC Adit

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMM ARBITRATION PETITION (L) NO. 130 OF 2020 Babaji Shivram Clearing & Carriers Pvt. Ltd.

...Petitioner

Versus

Bharat Heavy Electricals Limited

...Respondent

Ms Abhileen Chaturvedi a/w Mr Dhruv Jain i/b Economic Laws Practice for the Petitioner.

CORAM:

G.S. PATEL, J.

DATED:

13th February 2020 PC:- 1.

The petition is under Section 29-A of the Arbitration and Conciliation Act 1996. The Respondent is absent. 2.

Disputes arose between the parties under a Work Order dated 22nd November 2013. By an order dated 9th February 2018, an advocate of this Court was appointed as the sole arbitrator. The arbitrator entered upon the reference to his arbitration on 30th July 2018, and the matter proceeded before him.

13th February 2020

933-CARBPL130-20-I.DOC 3.

The original arbitral mandate was extended for six months by mutual consent. The extended arbitral mandate ended on 30th January 2020. The arbitral proceedings have reached the stage of cross examination of the Claimant's witness.

4.

Having regard to these circumstances, I am extending the arbitral mandate from 30th January 2020 until 1st March 2021 to complete the arbitral proceedings.

5.

The petition is disposed of accordingly.

(G. S. PATEL, J) 13th February 2020