IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMM ARBITRATION APPLICATION NO. 33 OF 2017 Doshi Engineering And Construction

...Petitioner

Versus

Indiabulls Construction Ltd

...Respondent

Ms Priyanka Kothari, with Prashant Phophale & Chaitanya Jadhav, i/b PMH Law for the Petitioner.

Mr Mayur Khandeparkar, with Tushar Gujjar, i/b Solicis Lex for the Respondent.

CORAM: G.S. PATEL, J DATED:

24th April 2017 PC:- 1.

Ms Kothari for the Petitioner agrees that by 26th May 2017 the Petitioner will place the entirety of its claim (including any documents in addition to those annexed to this Arbitration Application) before the Respondent's Head of Construction, Mr SS Kadyan. The representation will be made to the Head of Construction not by name but by designation. The Head of Construction will consider the claim in accordance with the Arbitration Clause 4.7.2.1 within 28 days and will communicate his decision in writing to the Petitioner thereafter. 24th April 2017

15-CARBA33-17 24-4.DOC 2.

The petition is disposed of in these terms leaving all rights and intentions open on both sides and with specific liberty to both sides to file a fresh Arbitration Application, if necessary. (G. S. PATEL, J.) 24th April 2017