← Library
Bombay High CourtCRR/11/2017disposed off

Shapoorji Pallonji And Company Ltd. v. Jignesh Shah And 4 ORS.

2017-02-07Hon'Ble Shri Justice S.J. Kathawalla1 pages

crr 11 of 2017 (906).sxw

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COURT RECEIVER'S REPORT NO.11 OF 2017 IN SUIT NO.1512 OF 2009 Shapoorji Pallonji and Co. Ltd.

...

Plaintiff versus Jignesh Shah and Ors.

...

Defendants WITH NOTICE OF MOTION NO.3030 OF 2016 IN SUIT NO.1512 OF 2009 Mr. Milind Sathe, Senior Advocate with Mr. Dhaval Vussonji, Ms. Sonam Mhatre, Mr. Umang Mehta, Ms. Saumya Brajmohan i/by M/s. Dhaval Vussonji and Associates, for Plaintiff and Applicant in NMS 3030 of 2016. Mr. Mayur Khandeparkar i/b Mr. J.P.Chandnani, for Respondent No.3. Mr. M.S.Deshpande, Court Receiver present.

CORAM: S.J. KATHAWALLA, J.

DATE: 7th FEBRUARY, 2017 P.C.:

1.

Time granted to the Plaintiff to complete construction is extended by six months from the date of this order. All contentions of Defendant Nos.1 to 5 qua the construction costs, the amounts payable to the Corporation etc., are kept open. Liberty to apply.

2.

The above Court Receiver's Report as well as Notice of Motion are disposed of.

( S.J.KATHAWALLA, J. ) ssp 1/1