New India Construction Co. v. Vijay Bahadur Avadh Narayan Singh And 8 ORS.
s 222 of 2018 (906).sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION SUIT NO.222 OF 2018 WITH NOTICE OF MOTION NO.360 OF 2018 New India Construction Co.
...
Plaintiff versus Vijay Bahadur Avadh Narayan Singh and Ors.
...
Defendants Mr. Hemant Mehta i/by M/s. Mehta and Co., for Plaintiff. Mr. A.R.Singh, for Defendants.
CORAM: S.J. KATHAWALLA, J.
DATE: 1 st MARCH, 2018 P.C.:
1.
The learned Advocates for the parties have tendered Consent Terms dated th February, 2018. They submit that the Consent Terms be taken on record and the above Suit be disposed of in terms of the Consent Terms. The Consent Terms are taken on record and marked 'X' for identification. The Consent Terms are signed by the Partner of the Plaintiff and the Defendants, who have been explained and interpreted the contents of the Consent Terms in Hindi by the Office of the Interpreter, High Court, Bombay. The Defendants are present in Court and they have informed the Court that they have understood the contents of the Consent Terms and have signed the same on their free will and volition and without any force, fraud and collusion. The Advocates for the parties have also signed the Consent Terms. The ssp 1/2
s 222 of 2018 (906).sxw undertakings recorded in the Consent Terms are accepted. The Suit is disposed of in terms of the Consent Terms, marked 'X'
. Refund of Court Fees, if any, as per rules. Notice of Motion also stands disposed of.
( S.J.KATHAWALLA, J. ) ssp 2/2