The B.E.S. And T. Undertaking v. M.P. Madhya Kkshetra Vidyut Vitran Co. Ltd And 4 ORS
sat 1/2 chs 283-2017.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION CHAMBER SUMMONS NO. 283 OF 2017 IN SUMMONS FOR JUDGMENT NO. 9 OF 2017 IN SUMMARY SUIT NO. 2956 OF 2004 R.R. Financial Consultant Ltd.
...Applicant In the matter between The B.E.S. & T. Undertaking ...Plaintiff vs.
M.P. Madhya Kshetra Vidyut Vitran Co. Ltd. & Ors. ...Defendants Ms.Radha Bhandari I/b. M.V. Kini & Co. for Plaintiffs. Mr.Netaji Gawade I/b. Sanjay Udeshi & Co. for Defendant No.1. Mr.Kalpesh Nansi with Farhana Khan for Defendant No.4 / Applicant. .
CORAM : S.C. GUPTE, J.
3 JULY 2017 P.C. :
Learned Counsel for Defendant No.4 has taken out a chamber summons for leave to file an affidavit in reply seeking leave to defend. There is a delay of 14 days in filing the reply. For the reasons stated in the affidavit in support of the chamber summons, the delay is condoned. Defendants No.4 tenders a reply to the summons for judgment. A copy is served across the Bar on the Advocates. The chamber summons is disposed of accordingly. ` Learned Counsel for Defendant No.1 seeks time to file a reply. As a last opportunity to Defendant No.1, four weeks' time is granted to file its reply to the summons for judgment.
sat 2/2 chs 283-2017.doc The summons for judgment to come up on board on 7 August 2017 for hearing.
(S.C. Gupte, J.)