Inder Kaishindas Ahuja v. Gopaldas Krishindas Ahuja And 8 ORS.
904-arbpl237-18 vai
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION (LODGING) NO.237 OF 2018 Inder K. Ahuja
...Petitioner
V/s.
Gopaldas K. Ahuja & Ors.
...Respondents
Ms.Anuja Karia i/b Mr.Shreeram Shirsat for the Petitioner. Mrs.Anita Castellino and Mr.A.R. Dwivedi i/b Lambay & Co. for the Respondent No.1.
Mr.Ganesh Ambekar i/b M/s.Thakore Jariwala & Associates for the Respondent No.2.
Ms.Sonu Tandon for the Respondent Nos.3 to 6. CORAM : R.D. DHANUKA, J.
DATE : 7TH MARCH, 2018.
P.C. :- 1.
By consent of parties, the time to make an award is extended by 12 weeks from 1st March, 2018. The matter is at the argument stage. The parties are directed to co-operate with each other and also with the learned arbitrator in rendering the award within the extended period. It is made clear that no further extension would be granted.
2.
The arbitration petition is disposed of in aforesaid terms. 1/2
904-arbpl237-18 No order as to costs. The petitioner is directed to convey this order to the learned arbitrator for compliance.
(R.D. DHANUKA, J.) 2/2