M/S. Electronic And Engineering Company (India) Pvt.Ltd. v. West Central Railway Ministry Of Railway And 4 ORS
Nitin 1 / 2 913-ARBPL-384-2015
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION (L) NO. 384 OF 2015 M/s. Electronic and Engineering Company (India) Private Limited ...
Petitioner
Versus
West Central Railway, Ministry of Railway & Ors.
...
Respondents Mr. V.M. Parkar for the Petitioner.
Mr. T. Pandian for the Respondents.
CORAM : S.J. KATHAWALLA, J.
DATED : 9 TH MARCH, 2015 P.C.
Heard the learned Advocates appearing for the parties and the following order is passed by consent :
i.
The General Manager, West Central Railway having his headquarters at Jabalpur shall appoint an Arbitrator in terms of clause 2900 of Standard Conditions of Contract within a period of four weeks from today.
ii.
The West Central Railway shall not invoke the following bank guarantees issued by the Petitioner until the learned Arbitrator passes his Award and for a period of six weeks thereafter if the Award is adverse to the Petitioner :
Nitin 2 / 2 913-ARBPL-384-2015 Sr. No.
Bank Guarantee No.
Date of Bank Guarantee 0061PEBG100082 09th September, 2010 0061PEBG10093 9th September, 2010 0061PEBG10049 12th May, 2010 0061PEB10050 12th May, 2010 iii.
The Petitioner undertakes to renew the aforestated four bank guarantees from time to time until the learned Arbitrator passes his Award and for a period of twelve weeks thereafter.
iv.
The above Petition is accordingly disposed of. (S.J. KATHAWALLA, J.)