IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION SUIT NO.761 OF 2008 Montrose Constructions Pvt. Ltd.

... Plaintiff V/s.

Shri Shamsunder Pundlik Dhumatkar ... Defendant Mr. Niket Jani, I/b Dhruve Liladhar & Co. for the Plaintiff. Mr. Siddhesh Bhole with Abdulla Cutlariwalla I/b Haresh Jagtiani & Associates for Defendant.

CORAM:

R. I. CHAGLA, J.

DATE:

10TH JUNE, 2019 PC:- 1.

The learned Counsel for the Plaintiff seeks permission to withdraw the Suit. Permission is granted. The Suit is dismissed as withdrawn.

2.

Refund of Court fees, if any, in accordance with the Rules. Today's date will be the date of claim for repayment. 3.

The Registry will issue certificate of refund of Court fees within three weeks upon production of an authenticated copy of this order.

( R I. CHAGLA, J. ) 1/1