← Library
Bombay High CourtCA/309/2016withdrawn

M/S Usha Chemicals Through Prop. Anuj Tibrewala v. Afcil Industries Ltd.

2017-10-04Hon'Ble Shri Justice K.R. Shriram1 pages

5.cp.1167.2015.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO. 1167 OF 2015 Normet India Ltd.

.. Petitioner Vs.

Hindustan Construction Company Ltd.

.. Respondent Ms.Minalghi Nimbalkar i/b Satyan S. Israni for petitioner. Ms.Prachi Ojbha i/b Advaya Legal for respondent. Mr.Shankar Kumar-Authorised Signatory of petitioner present. Mr.Nilesh Meker-Authorised Signatory of respondent present. CORAM : K.R.SHRIRAM, J.

DATE : 4TH OCTOBER 2017 P.C.

The counsels state that parties have amicably settled the matter and tendered consent terms. The consent terms dated 4th October 2017, signed by the authorised representative of petitioner, authorised representative of respondent and their respective advocates is taken on record and marked 'X' for identification.

Order in terms of the consent terms. Undertakings in the consent terms are accepted.

Petition accordingly stands disposed in terms of the consent terms. (K.R. SHRIRAM, J.) Shraddha Talekar PS 1/1