IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION SUIT NO.1011 OF 2011 WITH NOTICE OF MOTION NO.1338 OF 2014 IN SUIT NO.1011 OF 2011 Next Estates and Projects Pvt. Ltd.

....Plaintiff V/s.

Mohd. Redha Jaffer Mandil ....Defendant ---- Mr. Asif Vora i/b. Mr. Shoaib I. Menon for the plaintiff. Mr. Salim Shaikh, Managing Director of the plaintiff present. Mr. Denzil D'mello for the defendant.

Mr. Mohammed Redha Jaffer Mandil, defendant present. ---- CORAM : K.R.SHRIRAM,J DATE : 1st OCTOBER,2016 P.C.:- The counsel for the plaintiff and the defendant states that the parties have amicably resolved the matter and tendered consent terms. The consent terms dated 1st October, 2016 signed by the Managing Director of the plaintiff, the defendant and their respective advocates is taken on record and marked 'X' for identification. All undertakings given in the consent terms are accepted and so ordered. The suit accordingly stands disposed in terms of the consent terms. Interim application, if any also stands disposed. Gauri Gaekwad

2/2 902.S-1011-2011.doc Refund, if any of court fees in accordance with rules. (K.R.SHRIRAM,J) Gauri Gaekwad