Capacite Infraprojects Ltd. v. Radius Sumer Developers Pvt. Ltd.
Digitally signed by PRAJAKTA SAGAR VARTAK Date:
2022.06.22 15:01:00 +0530 PRAJAKTA SAGAR VARTAK 4-carbp 513-21
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL ARBITRATION PETITION NO. 513 OF 2021 Capacite Infraprojects Ltd.
...Petitioner
Vs.
Radius Sumer Developers Pvt. Ltd.
..Respondents ----- Mr. Dhruva Gandhi with Mr. Vaibhav Warerkar and Mr. Toufiq Kapadia i/ b. M. Mulla Associates for Petitioner.
----- CORAM : G.S. KULKARNI, J.
DATE : JUNE 21, 2022.
P.C.:
1.
Learned counsel for the petitioner seeks leave to withdraw this petition with liberty to file a fresh petition or appropriate proceedings as and when the need so arises.
2.
The petitioner would be fair in doing so, as it is quite clear that this petition was filed on 10 March, 2021, since then no orders were passed on this petition, as also the arbitration agreement has not been invoked so far.
3.
Accordingly, the petition is allowed to be withdrawn with liberty as prayed for.
4.
All contentions of the parties are expressly kept open. 5.
Disposed of. No costs.
[G.S. KULKARNI, J.]