M/S Amn Construction v. Golden Arrow Chs Ltd And ANR
918-CARBPL162-17.DOC Santosh
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMM ARBITRATION PETITION (L) NO.162 OF 2017 AMN Construction
...Petitioner
Versus
Golden Arrow CHS Ltd & Anr
...Respondents
Mr Ryan Menezes, i/b Jhangiani Narula & Associates, for the Petitioner.
Mr Shindore, i/b Ganesh M Kadam, for Respondent No.2. CORAM: G.S. PATEL, J DATED:
3rd May 2017 PC:- 1.
Parties have settled their disputes. Consent Terms tendered are taken on record and marked 'X' for identification with today's date. They are signed by the partner of the Petitioner and the Vice President of Respondent No.2. The Respondent No.1 is not a party to the Consent Terms, which are between the Petitioner and Respondent No.2.
2.
The Consent Terms are in order. They are not contrary to law. They have been drawn by the parties of their own volition in reflection of their true intentions.
3rd May 2017
918-CARBPL162-17.DOC 3.
The undertakings in the Consent Terms are accepted as an undertakings to the Court.
4.
The Petition is disposed of in accordance with the Consent Terms.
5.
A scanned copy of the Consent Terms is provided. It will be uploaded as the second order in this matter.
6.
All concerned to act on an authenticated copy of this order. (G. S. PATEL, J.) 3rd May 2017