← Library
Bombay High CourtARBP/396/2018

Adarsh Infrainterio Pvt Ltd v. Central Institute Of Fisheries Education

2018-03-28Hon'Ble Shri Justice R.D. Dhanuka1 pages

906-arbpl317-18 vai

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION (LODGING) NO.317 OF 2018 Adarsh Infrainterio Pvt. Ltd.

...Petitioner

V/s.

Central Institute of Fisheries Education

...Respondent

Ms.Nishita D'souza for the Petitioner.

Mr.Pushkal Mishra i/b M.V. Kini & Co. for the Respondent. CORAM : R.D. DHANUKA, J.

DATE : 28TH MARCH, 2018.

P.C. :- 1.

Learned counsel appearing for the parties jointly state that the arguments are already complete. The last meeting is however being held on 31st March, 2018 for seeking certain clarification by the learned arbitrator. The statement is accepted. 2.

The time to make an award is extended by three months with effect from 28th February, 2018. It is made clear that no further extension of time would be granted.

3.

The parties are directed to convey this order to the learned arbitrator for compliance.

4.

The arbitration petition is disposed of in aforesaid terms. No order as to costs.

(R.D. DHANUKA, J.) 1/1