Kotak Mahindra Prime Ltd. v. Shri Doehle Danautic India Pvt. Ltd. And Anoter
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION IAL/1774/2020 IN EXAL/2593/2018 IAL/1778/2020 IN EXAL/2591/2018 IAL/1769/2020 IN EXAL/2588/2018 IAL/1771/2020 IN EXAL/2592/2018 IAL/2076/2020 IN EXAL/2590/2018 IAL/1772/2020 IN EXAL/2595/2018 IAL/2071/2020 IN EXAL/2585/2018 IAL/1770/2020 IN EXAL/2587/2018 Kotak Mahindra Prime Limited ... Claimant
Versus
Abid Ali Basusaheb Shaikh ... Respondent Shir Satya Amar Jeet and Anr.
... Respondents PMC Krishna ... Respondent Nisar Ismail Shaikh ... Respondent Mahesh Narendra Alimchandani ... Respondent Farooque Yusuf Darjee and Anr.
... Respondents Doehle Danautic India Pvt. Ltd.
... Respondent Anuradha Real Estate Developers Pvt. Ltd. and Anr. ... Respondents Mr. Vishal Tambat for the Applicant-Claimant. None for the Respondents.
CORAM : A. K. MENON, J.
TH DECEMBER, 2020.
DATED : 16 P.C. :
1.
These interim applications seek restoration of the Execution Applications, which came to be dismissed by the Prothonotary and Senior Master. Perused the applications. Heard learned counsel for the applicants. 1/2 5-IAL-1774-2020-Group.doc Dixit
2.
In my view, one more opportunity can be granted to comply with the office objections. Accordingly, I pass the following order :- (i) All interim applications are allowed in terms of prayer clauses (a) and (b).
(ii) If office objections are not removed on or before 13 th January 2021, the Execution Applications shall stand rejected without any further order of the court and no application to restore the same will be entertained.
(A. K. MENON, J.) by Sneha A.
Dixit Date:
2020.12.17 11:28:57 +0530 Sneha A. Dixit 2/2 5-IAL-1774-2020-Group.doc Dixit