Usha H.Dalal v. 1(A) Lilaben Manibhai Patel And ORS. And Millennium Developers Pvt. Ltd.
crr 161 of 2016 (908).sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COURT RECEIVER'S REPORT NO.161 OF 2016 IN SUIT NO.120 OF 1978 Usha H. Dalal ...
Plaintiff
Versus
Lilaben Manibhai Patel and Ors.
...
Defendants and Millennium Developers Pvt. Ltd.
...
Respondent Mr. Rahul Datia Director of Respondent, present. Mr. G.G.Ketkar, 1 st Assistant to Court Receiver, present.
CORAM: S.J. KATHAWALLA, J.
DATE: 5 th APRIL, 2016 P.C.:
1.
Perused the Report. The Report is allowed in terms of prayer clauses (a), (b) and (c) , which are reproduced hereunder :
"(a)the Court Receiver be discharged without passing accounts; (b)the Plaintiff/Defendants be directed to pay a sum of Rs.62,231/- towards the costs, charges and expenses of the Court Receiver as per the provisional statement of account;
(b)Cost of this Report may be fixed at Rs.3,000/- and the same may be permitted to be recovered from parties to the suit; 2.
The Director of the Respondent undertakes to pay the dues of the Court Receiver within a period of two weeks from today. The undertaking is accepted. The Report is accordingly disposed off.
( S.J.KATHAWALLA, J. ) ssp 1/1