IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO.817 OF 2014 Haldia Nirman Projects Private Limited

...Petitioner

vs Shapoorji Pallanji And Company Limited

...Respondent

.....

Mr. Sugata Maiti, i/b. Legal Links, for the Petitioner. Mr. Ashish Kamat, a/w. Mr. Anoj Menon and Ms. Debashree Dey, i/b. Desai & Diwanji, for the Respondent.

......

CORAM : S.C. GUPTE, J.

DATED: APRIL 22, 2016 P.C. :

.

By consent of Counsel on both sides, this Company Petition is disposed of in terms of the following order :- 2.

Mr. Ranjan Bachavat, Senior Advocate, is appointed as a sole Arbitrator to adjudicate upon the disputes and differences between the parties, which are the subject matter of the Company Petition herein. 3.

The learned Arbitrator shall conduct the arbitral proceedings and charge fees for arbitration in accordance with the amended Schedule IV of the new Act. The learned Arbitrator shall endeavour to dispose of the arbitral proceedings latest by 31 December 2016. All rights and contentions of the parties, on merits, are kept open. No order as to costs.

( S.C. GUPTE, J. ) Pg 1 of 1