IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION (L) NO.1122 OF 2015 The Kurla Industrial Premises

...Petitioner

Co-op.Society Ltd.

v/s.

The State of Maharashtra & Ors.

...Respondents

...

Mr.M.J.Jamdar, Advocate, for the Petitioner.

Mr.J.S.Saluja, AGP, for the Respondent - State. ...

CORAM : A.A. SAYED, J.

DATED : 27 JULY 2015 P.C.:

Learned Counsel for the Petitioner seeks leave to withdraw the Petition with liberty take recourse to the alternate remedy available in law. 2.

The Petition is allowed to be withdrawn with liberty as prayed. 3.

The statement of the learned Counsel for the Petitioner is recorded that the Petitioner would file an Appeal alongwith an Application seeking stay of the impugned order before the the State Government within four weeks from today.

4.

The State Government shall decide the Application of stay with necessary condition of deposit/payment, if any, within six weeks thereafter. Uday P. Kambli 1/2

2/2 wpl-1122-15.doc 5.

Until the Application for stay is decided, no coercive steps be taken against the Petitioner.

6.

The Petition is disposed of in the aforesaid terms. (A.A. SAYED, J.) Uday P. Kambli 2/2