← Library
Bombay High CourtS/553/2014consent term

Raghvendra Construction Co. Pvt. Ltd. v. Shenaz Alamgir Shaikh And ANR.

2015-02-05Hon'Ble Shri Justice G.S. Patel2 pages

PROD-S553-14.DOC Agk

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION SUIT NO. 553 OF 2014 Raghvendra Construction Co. Private Limited ...Plaintiffs

Versus

Shehnaz Alamgir Shaikh & Ors.

...Defendants Mr. Shailendra Singh, i/b M/s. J.P. Consultia, for the Plaintiffs. Mr. A.L.N. Khatri, for Defendants Nos. 1 & 2. CORAM: G.S. PATEL, J DATED:

5th February 2015 PC:- 1.

Not on board. Mentioned. Taken on board.

2.

The Suit is being settled. Defendants Nos. 3 to 10 are sought to be deleted. Leave to amend to delete Defendants Nos. 3 to 10. Amendment to be carried out on or before 10th February 2015. 3.

As between Plaintiff and Defendants Nos. 1 and 2, the Suit is settled. Consent Terms are tendered. These are signed by the Director / Authorized Representative of the Plaintiff, Advocates for the Plaintiff, Defendants Nos. 1 and 2 and their Advocates.

PROD-S553-14.DOC Defendants Nos. 1 and 2 are personally present in Court, as is Mr. Raghu M. Poojari, Director / Authorized Signatory of the Plaintiff. 4.

The Consent Terms along with their annexures are taken on record and marked "X" for identification. Undertakings in the Consent Terms are accepted as undertakings to the Court. 5.

The Suit is disposed of in accordance with the Consent Terms.

6.

Refund of court fee, if any, in accordance with the Rules. 7.

All concerned to act on an authenticated copy of this order. (G. S. PATEL, J.)