IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION Commercial Arbitration Application NO. 143 OF 2019 Ambika Structures And Developers LLP ...Applicant

Versus

Eisha Vastu Construction And Ors.

...Respondents

---- Mr.Karan Bhosale with Varun Satiya, Ms.Pratyusha Pamchangani i/b. Crawford Bayley & Co., for the Applicant. Mr.Prasad G.Keluskar i/b. Pavan Patil, for Respondent no.3. Mr.Vijay Upadhyahy, for Respondent no.5.

----- CORAM : G.S. KULKARNI, J.

DATE : 18th October, 2019 P.C.:

1.

Heard learned Counsel for the applicant and learned Counsel for respondent nos.3 and 5.

2.

Learned Counsel for respondent no.5 has raised an objection that as the agreement in question is executed at Pune as also the arbitral tribunal which was appointed earlier was conducting arbitral proceedings at Pune, the application is required to be fled at the Appellate side of this Court. 3.

Let this application be accordingly transferred to the Appellate Side of this Court and be numbered accordingly. [G.S. KULKARNI, J.]