The Commissioner Of Central Excise Pune-Iii v. M/S. Eon Hinjewadi Infrastructure (P) Ltd.
NMA-789-2014 Dond
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION NOTICE OF MOTION NO.789 OF 2014 IN CENTRAL EXCISE APPEAL (L)NO.110 OF 2014 The Commissioner of Central Excise ..Applicant Vs.
M/s Eon Hinjewadi Infrastructure (P)Ltd.
..Respondent ----- Mr. J.B. Mishra for Applicant.
Mr. J. Sanghavi i/b PDS Legal for Respondent. ---- CORAM: B.R. GAVAI & A.S. GADKARI, JJ.
DATE : 13th April 2015.
P.C.:
This Notice of Motion is taken out for condonation of delay of 133 days in filing the appeal. The motion is opposed by the learned Counsel appearing for the Respondents.
However, taking into consideration the averments made in the affidavit, we are inclined to condone the delay. The delay is condoned. The Notice of Motion is allowed. (A.S. GADKARI, J.) (B.R. GAVAI, J.)
NMA-789-2014