← Library
Bombay High CourtCHS/683/2015withdrawn

L And T Finance Ltd. v. M/S. Vantage Infrastructures Pvt. Ltd. And ANR.

2019-03-14Hon'Ble Shri Justice G.S. Patel1 pages

919-CHS683-15.DOC Arun

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION CHAMBER SUMMONS NO. 683 OF 2015 WITH EXECUTION APPLICATION NO. 2293 OF 2015 L&T Finance Limited ...Claimant

Versus

Vantage Infrastructure Pvt Ltd & Anr ...Defendants Ms Jalpa Pithadia, i/b SI Joshi & Co, for the Claimant. CORAM: G.S. PATEL, J DATED:

14th March 2019 PC:- 1.

At the request of Ms Pithadia for the Claimant, the Execution Application is dismissed as withdrawn.

2.

In view of this, the Chamber Summons does not survive and accordingly it is dismissed.

(G. S. PATEL, J) 14th March 2019