Bombay High CourtWP/1380/2018

Ashok Jaiswar And 2 ORS v. The Commissioner, Municipal Corporation Of Greater Mumbai And 2 ORS

2018-04-26Hon'Ble Shri Justice S.C. Gupte2 pages

Chittewan 1/2

905. WPL 1411-18.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION (L) NO.1411 OF 2018 Ashok Jaiswar And Others ...

Petitioners

Versus

The Commissioner, Municipal Corporation of Greater Mumbai And Another ...

Respondents .....

Mr. Sharique Nachan I/b Judicare Law Associates for the Petitioners. Mr. Ashwin Sakolkar a/w Ms. Pooja Yadav for Respondent Nos.1 And 2MCGM. Mr. Yadunath Chaudhari a/w Mr. Chinmaya Acharya for Respondent No.3. ....

CORAM : S.C. GUPTE, J.

DATE : 26 APRIL 2018 P.C. :

.

This petition challenges a speaking order passed by the Assistant Engineer, Municipal Corporation of Greater Mumbai, under Section 351 of the Mumbai Municipal Corporation Act, 1888. The speaking order was passed in pursuance of a notice to show cause issued to about twenty five structures existing on the suit plot including the structures covered by the present petition. In sofar as other structures are concerned, similar writ petitions filed by their respective occupants have been considered by this Court and dismissed by an order dated 19 April 2018. For the same reasons, discussed in the order dated 19 April 2018, even this petition has no merit and is dismissed.

Chittewan 2/2

905. WPL 1411-18.doc As in the case of Writ Petition (L) No.942 of 2018 dismissed by the order dated 19 April 2018, the ad-interim protection against coercive steps in pursuance of the impugned order shall extend upto 10 May 2018. (S.C. GUPTE, J.)