Mahavir Construction v. Parth Developers
arbp 890 of 2014 (925).sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO.890 OF 2014 Mahavir Construction ...
Petitioner versus Parth Developers ...
Respondent Mr. Shabbir Rassiwala, for Petitioner.
Mr. M.U.Pandey, for Respondent.
CORAM: S.J. KATHAWALLA, J.
DATE: 13th JANUARY, 2015 P.C.:
1.
The learned Advocates appearing for the parties have tendered Consent Terms dated 13-01-2015. They submit that the Consent terms be taken on record and the Arbitration Petition be disposed of in terms of the Consent Terms. The Consent Terms are taken on record and marked 'X' for identification. The Consent Terms are signed by the Partner of the Petitioner and the Partner of the Respondent. The Consent Terms are also signed by the Advocates for the parties. The above Arbitration Petition is disposed of in terms of the Consent Terms, marked 'X'.
( S.J.KATHAWALLA, J. ) ssp 1/1