Bombay High CourtCARAP/158/2019disposed off

Bothe Windfarm Development Pvt. Ltd. v. The New India Assurance Co. Ltd.

2019-06-06Hon'Ble Shri Justice G. S. Kulkarni1 pages

904 CARAPL 217 OF 2019 vks

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION APPLICATION (L) NO.217 OF 2019 Bothe Windfarm Development Pvt. Ltd.

...

Applicant.

V/s.

The New India Assurance Co.Ltd.

...

Respondent Mr. Ashwin Shankar a/w Mr. Rishi Morarka, for the applicant.

CORAM : G. S. KULKARNI, J.

DATE : 6th June 2019.

P.C. :

After this application was heard for some time, learned counsel for the applicant submits that as a suit is already instituted by the petitioner in January, 2019 against the respondent on this very issue, he would like to withdraw this application with liberty pursue appropriate proceedings. Allowed to be withdrawn with liberty as prayed for. No costs. [G. S. KULKARNI, J] 1/1