Bombay High CourtCP/43/2014disposed off

Balajee Infratech And Consturctions Pvt.Ltd. Rep. By Its Sr.Manager(Procurement) Mr.K.Muraleedharan v. M/S.Shapoorji Pallonji And Company Ltd. Cin No.U45200mh1943plc003812

2015-09-29Hon'Ble Shri Justice S.C. Gupte2 pages

911.cp.43.2014.doc dik

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO. 43 OF 2014 Balajee Infratech & Construction Pvt. Ltd.

...Petitioner

vs Shapoorjee Pallodji & Co. Ltd.

...Respondent.

.....

Mr Ashok S Daver a/w M.S.Roy i/b Gauri S Rao for the Petitioner Mr Venkatesh Dhond, Sr. Advocate a/w Ms Debashree Dey i/b Desai & Diwanji for the Respondent.

.....

CORAM : S.C. GUPTE, J.

SEPTEMBER 29, 2015 P.C. :

By consent of parties, the Petition is disposed of by appointing Mr Naushad Engineer, Advocate, as a Sole Arbitrator to adjudicate upon the disputes and differences between the parties, which are covered by the Company Petition herein. The Sole Arbitrator shall complete the hearing of the reference and make his award within a period of six months from today. It will be open to the Petitioner to apply for interim relief before the Sole Arbitrator on the ground that corresponding payment has already been released in respect of particular works by the Principal of the Respondent. All rights and contentions of the parties on merits are kept open. There shall be no order as to costs. ( S.C.GUPTE J. ) Pg 1 of 2

911.cp.43.2014.doc CERTIFICATE Certified to be true and correct copy of the original signed Judgment/ Order.