Bank Of Baroda v. M/S Hydro Engineers And ANR
crr 344 of 2015 (903).sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COURT RECEIVER'S REPORT NO.344 OF 2015 IN SUIT NO.2158 OF 1993 Bank of Baroda ...
Plaintiff
Versus
M/s. Hydro Engineers and Anr.
...
Defendants None present for the parties.
Mr. G.G.Ketkar, 1 st Assistant to Court Receiver, present.
CORAM: S.J. KATHAWALLA, J.
DATE: 5 th APRIL, 2016 P.C.:
1.
Perused the Report. The same is allowed in terms of prayer clauses (a) and (b), which are reproduced hereunder :
(a) Court Receiver be discharged without passing accounts and Plaintiff may be directed to pay costs, charges and expenses of the Court Receiver, as per the provisional statement prepared by this Registry upon taking inspection;
(b)that the cost of and incidental to this report be fixed at Rs.3,000/- and the Plaintiff may be directed to deposit the same in the office of the Court Receiver;
2.
The dues of the Court Receiver including costs and expenses shall be paid by the Plaintiff Bank within two weeks from the date of this order. The Report is accordingly disposed of.
( S.J.KATHAWALLA, J. ) ssp 1/1