← Library
Bombay High CourtIA/65/2021disposed off

1a Nikhil Daji Hatankar And 2 ORS. v. Ankur Corporation Builders And Developers And Another

2021-01-14Hon'Ble Shri Justice A. K. Menon1 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 65 OF 2021 IN EXECUTION APPLICATION NO. 1068 OF 2019 Nikhil Daji Narayan Hatankar & Ors.

...

Decree Holders vs M/s. Ankur Corporation Builders ...

Respondents And Developers & Anr.

Ms. Vidya Nair i/b. Ms. Alisha Pinto for the Decree Holders. None for the Respondent.

CORAM : A. K. MENON, J.

th JANUARY, 2021 DATE : 14 P.C. :

1.

The interim application seeks amendment to the Schedule at Exhibit B. In view thereof I pass the following order : (i) Delay is condoned.

(ii) Amendment in terms of Exhibit B is permitted. (iii) Interim Application is disposed.

(A.K.MENON, J.) by Rajeshwari R.

Pillai Date: 2021.01.14 17:24:20 +0530 Rajeshwari R. Pillai 1/1 7-IA-65-2021-EXA-1068-2019.doc rrpillai