Sheth Developers Pvt.Ltd v. Nina Concrete System Pvt.Ltd
2.cp.120.2016.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO. 120 OF 2016 WITH COMPANY APPLICATION (LODG.) NO. 335 OF 2018 Nina Concrete Systems Pvt. Ltd.
.. Petitioner Vs.
M/s. Sheth Developers Pvt. Ltd.
.. Respondent Mr.Anil Jarial I/b Legal Associates for petitioner. Mr.Nitin Thakkar, senior advocate a/w. Mr.Manish P. Getay and Mr. Raju Yamgar I/b Raju Yamgar for respondent.
Ms.Hetal Parikh, Director/Authorized Signatory of petitioner present. Mr.Ashwin N. Sheth, Director of respondent present. CORAM : K.R.SHRIRAM, J.
DATE : 24TH JULY 2018 P.C.
In the order dated 13th July 2018, in appearance 'Mr.Ania Jariag' is corrected to read as as 'Anil Jarial.'
Parties have entered into consent terms dated 16th July 2018. The consent terms signed by the Director of petitioner/authorized signatory of petitioner, Director/authorized signatory of respondent and their respective advocates is taken on record and marked 'X' for identification. Shri Thakker and Shri Anil Jarial state that the signatories to the consent terms are present in Court and identify their respective clients. Shraddha Talekar PS 1/2
2.cp.120.2016.doc Shri Jarial for petitioner states that the installments mentioned in Paragraph 18(i) and (ii) have been received.
Order in terms of consent terms. All undertakings in the consent terms accepted.
Since the petition is yet to be advertised after admission, the petition disposed in terms of the consent terms.
In view of above, Company Application (lodg.) No. 335 of 2018 stands disposed.
Within two weeks, all office objections to be removed and application to be numbered.
(K.R. SHRIRAM, J.) Shraddha Talekar PS 2/2