← Library
Bombay High CourtCARBP/918/2019disposed off

Shivlok Construction v. Mahaveer Infra Engineering Private Limited And 2 ORS

2019-12-12Hon'Ble Shri Justice G.S. Patel2 pages

928-CARBP918-19-.DOC Shephali

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMM ARBITRATION PETITION NO. 918 OF 2019 Shivlok Construction

...Petitioner

Versus

Mahaveer Infra Engineering Pvt Ltd & Ors

...Respondents

Ms Achala Hatode, i/b SK Jain & Associates, for the Petitioner.

Mr Firoz Pathan, i/b Niraj Agrawal, for Respondents Nos. 1 & 2.

CORAM:

G.S. PATEL, J.

DATED:

12th December 2019 PC:- 1.

This is a Petition under Section 29-A of the Arbitration and Conciliation Act 1996. Mr Vishal Kanade was appointed as an Arbitrator on 28th October 2016. He entered upon the reference to his arbitration soon thereafter. The evidence of the Claimant is complete and the cross-examination of the respondent's first witness is underway.

2.

Parties agreed to an initial extension of six months. The arbitral mandate ended on 29th April 2019.

3.

Time is extended till 12th June 2020.

12th December 2019

928-CARBP918-19-.DOC 4.

The Petition is disposed of accordingly. There will be no order as to costs.

(G. S. PATEL, J) 12th December 2019