Bombay High CourtNMW/293/2018disposed off

Crystal Construction Company v. Additional Controller Of Stamps And 2 ORS

2018-08-06Hon'Ble Shri Justice G.S. Patel2 pages

33-NMW293-18.DOC Shephali

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION NOTICE OF MOTION NO. 293 OF 2018 IN WRIT PETITION NO. 714 OF 2018 Crystal Construction Co

...Petitioner

Versus

Additional Controller of Stamps & Ors

...Respondents

Mr Ravi Gadagkar, with MR Aniket Ransubhe, i/b Ajay Basutkar, for the Applicant/Petitioner.

Mr Abhay Patki, Additional GP, for Respondents Nos. 1 to 3. CORAM: G.S. PATEL, J DATED:

6th August 2018 PC:- 1.

The prayer in the Motion is same as the final prayer (b) in the Writ Petition itself. Rule was issued on 6th November 2017 in the writ petition.

2.

This relief cannot be granted in the Notice of Motion. All that can be done now is to list the matter at an early date for hearing and final disposal.

6th August 2018

33-NMW293-18.DOC 3.

Affidavit in Reply to the Writ Petition to be filed and served on or before 7th September 2018. Affidavit in Rejoinder, if any, to be filed and served on or before 24th September 2018. 4.

List the Writ Petition for hearing and final disposal on 3rd October 2018, high on board.

5.

The Notice of Motion is infructuous and it is disposed of as such.

(G. S. PATEL, J) 6th August 2018