← Library
Bombay High CourtCP/536/2016disposed off

M/S. Simplex Infrastructures Limited v. M/S. Essar Projects (India) Ltd., Cin Nou99999mh1989plc053280

2018-06-28Hon'Ble Shri Justice K.R. Shriram1 pages

901.cp.536.2016.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO. 536 OF 2016 M/s. Simplex Infrastructures Limited .. Petitioner Vs.

M/s. Essar Projects (India) Ltd.

.. Respondent Ms. Chaitrika Patki I/b Vidhii Partners for petitioner. Ms.Kritika Sethi I/b Cyril Amarchand Mangaldas for respondent. CORAM : K.R.SHRIRAM, J.

DATE : 28TH JUNE 2018 P.C.

After the petition was admitted by this Court on 29th November 2016, the National Company Law Tribunal, Mumbai (NCLT) has admitted a petition against the company and moratorium under Section 14 of Insolvency and Bankruptcy Code, 2016 has been granted by an order dated 20th April 2018. In view thereof, this petition cannot be proceeded with. Ms.Patki for petitioner states that petitioner has thereafter lodged its claim with the Insolvency Resolution Professional (IRP). In view thereof, Ms.Patki states that they will pursue their claim with the IRP, who shall consider it in accordance with law.

Company Petition accordingly disposed.

(K.R. SHRIRAM, J.) Shraddha Talekar PS 1/1