IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION Commercial Arbitration Petition No.72 OF 2022 Ghatkopar Aditya CHSL.

..Petitioner Vs.

Kumar Builders Project Pune Pvt.Ltd. & Ors. ..Respondents and Commercial Arbitration Petition No.121 OF 2022 Kumar Builders Project Pune Pvt.Ltd. & Ors. ..Petitioners Vs.

Ghatkopar Aditya CHSL & Ors.

..Respondents ----- Mr.M.M.Vashi, Senior Advocate with Ms.Riya Jain, for the Petitioner in CARBP 72/22 and for Respondent Nos.1 and 2 in CARBP 121/22. Mr.Malcolm Siganporia with Bipin Joshi, Vedanshi Shah i/b. Bipin Joshi, for the Petitioner in CARBP 121/22 and for Respondents in CARBP 72/22.

----- CORAM :

G.S. KULKARNI, J.

DATE :

JUNE 29, 2022.

P.C.:

1.

Learned Counsel for the parties have tendered consent minutes of the order by which the parties pray that both the Section 9 petitions be disposed of. The parties are also agreeable for disputes and differences between the parties to be referred to arbitration by appointing a sole arbitrator, and of an interim arrangement in the Section 17 application is decided. 2.

The consent minutes of the order are signed by the Advocates for the respective parties. They are accordingly, taken on record and marked "X" for identification.

3.

Both the petitions stand disposed of in terms of the minutes of the order. No costs.

[G.S. KULKARNI, J.]