Shidu Shripati Holkar v. The Official Liquidator Of Patheja Brothers Forgings And Stamping Ltd( In Liqn)
kvm 1/1 43-CA276.19
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY APPLICATION NO. 276 OF 2019 IN COMPANY PETITION NO. 95 OF 1999 Shidu Shripati Holkar ..... Applicant
IN THE MATTER BETWEEN
Devi Construction ..... Petitioner
VERSUS
The Official Liquidator of M/s.Patheja Brothers Forgings & Stamping Ltd. (In Liqn.) ..... Respondent Ms.Molina P. Thakur for the Applicant.
Mr.Mahendhar Aithe, Company Prosecutor to the Official Liquidator present.
CORAM :
R.D. DHANUKA, J.
DATE :
28th NOVEMBER, 2019 P.C.
The applicant is ex-worker, seeks condonation of delay of 1,654 days in filing affidavit of claim of the applicant and has explained delay in paragraphs (5) and (6) of the affidavit in support of the company application. The reasons recorded therein are accepted. Company application is made absolute in terms of prayer clauses (a) and (b). No order as to costs.
[R.D.DHANUKA, J.]