Paresh Constuctions v. Jai Hanuman Co-Op. Hsg Soc. Ltd.
mp 1/2 19 ARBP 1025-2019.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 1025 OF 2019 Paresh Constructions
...Petitioner
Versus
Jai Hanuman Co-Op. Hsg. Soc. Ltd.
...Respondent
---- Mr. Atharva Sanghvi i/b M/s. Praxis Legal for Petitioner. ---- CORAM : G. S. KULKARNI, J.
DATE : 05th SEPTEMBER 2019 P.C.:
1.
This is a petition fled under Section 29-A of the Arbitration and Conciliation Act, 1996 whereby the petitioner has prayed for extension of time by six months to enable the Arbitral Tribunal to complete the arbitral proceedings and publish an award. It is submitted that, petitioner's evidence is over and last witness of the respondents would be examined.
2.
Having perused the averments in the petition, the mandate of the Arbitral Tribunal to conclude the arbitral proceedings and publish an award is required to be extended. Accordingly, the petition is granted in terms of prayer clause (a) which reads thus. "That this Hon'ble Court may be pleased to extend the mandate of the Learned Arbitrator for a period of nine months with efect from 18.03.2019."
mp 2/2 19 ARBP 1025-2019.doc 3.
Ordered accordingly.
4.
Disposed of. No costs.
(G. S. KULKARNI, J.)