Bombay High CourtARBP/511/2017withdrawn

Punj Lloyd Limited v. Mumbai Port Trust And 2 ORS

2017-07-31Hon'Ble Shri Justice S.C. Gupte2 pages

1/2 ARBPL-621-2017.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION (L) NO.621 OF 2017 Punj Lloyd Limited ....Petitioner Vs.

Mumbai Port Trust and Ors.

....Respondents ---- Mr. Venkatesh Dhond, senior advocate a/w. Mr. Waseem Pangarkar and Mr. Abhishek Gupta i/b. MZM Legal for petitioner. Mr. Dinyar Madon, senior advocate a/w. Mr. Shahen Pradhan and Ms. Ashwini Hariharan i/b. HSA Advocates for respondent no.1 (Mumbai Port Trust).

Mr. Arun Kumar, General Manager of petitioner present in person. ---- CORAM : K.R.SHRIRAM, J.

DATE : 31st JULY, 2017 P.C.:

Not on board. Upon mentioning taken on board. At the outset, Mr. Dhond, senior counsel for petitioner tenders draft amendment and seeks leave to amend the petition as per the draft amendment. The draft amendment is taken on record and marked 'X' for identification.

Leave to amend as per the draft amendment is granted. Amendment to be carried out within one week from today. The petition was heard for some time. When the Court was about to dictate the order, Mr. Dhond, on instructions from Mr. Arun Kumar, General Manager of petitioner, sought leave to withdraw the petition. Gauri Gaekwad

2/2 ARBPL-621-2017.doc Therefore, the petition dismissed as withdrawn. (K.R. SHRIRAM, J.) Gauri Gaekwad