Parwan Constructions Pvt. Ltd. v. Ranjitsingh Linga And 2 ORS.
nma.1174.15.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION NOTICE OF MOTION NO. 1174 OF 2015 IN APPEAL (LODGING) NO. 555 OF 2015 IN NOTICE OF MOTION NO. 3008 OF 2010 IN SUIT NO. 2678 OF 2010 Parwan Constructions Pvt. Ltd.
...Applicant
IN THE MATTER BETWEEN :
Parwan Constructions Pvt. Ltd.
...Appellant
Versus
Ranjitsingh Linga & Ors.
...Respondents
Ms. Vidita Bhalekar I/b Mr. Sameer Bhalekar for the Applicant/Appellant None for the Respondents CORAM : V. M. KANADE & REVATI MOHITE DERE, JJ.
TUESDAY, 15TH DECEMBER, 2015 P.C. :
1.
Heard learned Counsel appearing on behalf of the applicant/appellant. None appears on behalf of the respondents, though served.
2.
Delay of 66 days in filing appeal is condoned for reasons stated in paras 4 and 5 of the affidavit in support of the Notice of Motion. SQ Pathan 1/2
nma.1174.15.doc 3.
Motion accordingly is allowed and disposed of. 4.
Appeal to be heard along with Appeal Nos. 303 of 2015, 324 of 2015 and Appeal (Lodging) Nos. 509/2015 and 555 of 2015. REVATI MOHITE DERE, J.
V. M. KANADE, J.
SQ Pathan 2/2