Gulraj Constructions v. The Institute Of Cost Accountants Of India
17 ARBP 915 OF 2019 vks
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION (L) NO. 915 OF 2019 Gulraj Constructions ...
Petitioner V/s.
The Institute ofCost Accountants of India ...
Respondents Mr. Arthav Sanghvi i/by Praxis Legal, for the Petitioner. CORAM : G. S. KULKARNI, J.
DATE : 19th September, 2019.
P.C. :
1] This petition is filed under Section 29A of the Arbitration and Conciliation Act, 1996 (for short called as, "the Act"), whereby the petitioner prays for extension of the mandate of the arbitral tribunal to conclude the arbitral proceeding and to publish an award.
2] It is informed that the respondents are served. However, none appears for the respondent. Learned counsel for the petitioner submits that the oral evidence of the respondents is in progress.
3] Having heard learned counsel for the petitioner and perusal of the averments as made in the petition, in my opinion, in the interest of justice the mandate of arbitral tribunal is extended for a period of six months from today.
1/2
17 ARBP 915 OF 2019 4] The arbitral tribunal shall endeavour to conclude the arbitral proceedings and publish award within the extended period. 5] The petition is disposed of in the above terms. No costs. [G. S. KULKARNI, J] 2/2