IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 373 OF 2022 Kings Builders and Developers .. Petitioner Vs.

Nehru Nagar Shramasafalya CHS Ltd.

.. Respondent Mr. Vivek Patil i/b.Vivek Patil & Associates for the petitioner. Mr. Moin Khan i/b. Vishal Ghosalkar for the respondent. CORAM : G.S. KULKARNI, J.

DATE : AUGUST 29, 2022.

P.C.:

1.

Not on board. Upon mentioning, taken on board on a praecipe as moved on behalf of the respondent.

2.

This is a petition filed under section 29-A of the Arbitration and Conciliation Act, 1996 (for short "the Act") for extension of the mandate of the arbitral tribunal.

3.

Learned counsel for the parties submit that the arbitral proceedings are at the final stage inasmuch as the final arguments of the parties have been heard by the arbitral tribunal. 4.

At the joint request of the parties, the mandate of the arbitral tribunal to conclude the arbitral proceedings is extended finally for a period of two months from today.

[G.S. KULKARNI, J.]