IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO.968 OF 2014 GE India Industrial Pvt. Ltd.

....Petitioner V/s.

Unity Infraprojects Limited ....Respondent COMPANY APPLICATION NO.683 OF 2015 IN COMPANY PETITION NO.443 OF 2014 State Bank of India ....Petitioner V/s.

Unity Infraprojects Limited ....Respondent ---- Mr. Gandhar Raikar i/b. Charles J De'souza for the petitioner. Mr. Aashish Kamat i/b. Vidhii Patners for the respondent. Ms. Jasmine Upadhye i/b. M.V. Kini & Co. for State Bank of India. ---- CORAM : K.R.SHRIRAM,J DATE : 22nd December, 2015 P.C.:- The parties have amicably settled the matter by entering into consent terms dated 22nd December, 2015 signed by the authorised representatives of the petitioner, the respondent and their respective advocates.

Order in terms of consent terms which is taken on record and marked 'X' for identification. The undertakings given in the consent terms are accepted and so ordered.

Gauri Gaekwad

14.CP-968-2014 The petition accordingly stand disposed. All company applications pending also stand disposed.

(K.R.SHRIRAM,J) Gauri Gaekwad