M/S Indusind Bank Limited v. Ashok Dayalji Gori And ANR
44-EXA 398.2017.doc K.S. Jadhav
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION EXECUTION APPLICATION NO.398 OF 2017 IndusInd Bank Ltd.
... Claimant
Versus
Ashok Dayalji Gori & Anr.,
...Respondents
---------- None present for Applicant/Claimant.
---------- CORAM : R.I. CHAGLA J DATE : 9TH JANUARY, 2023.
ORDER :
1.
The Execution Application has been placed for dismissal under Rule 329 of the Bombay High Court Original Side Rules, 1980. 2.
This is due to non prosecution of the application for execution for a period in excess of 12 months from the date of filing of the application as provided in the said Rule.
3.
Considering that none appears for the Applicant and the Execution Application is not being proceeded with, the Execution Application is dismissed for non prosecution. [R.I. CHAGLA J.] 1/1