IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION CONTEMPT PETITION NO. 81 OF 2013 IN APPEAL NO. 367 OF 2009 IN SUMMONS FOR JUDGEMNT NO. 08 OF 2008 IN SUMMARY SUIT NO. 2536 OF 2007 Slum Rehabilitation Authority ... Petitioner.

V/s.

The State Bank of India & Anr.

... Respondents.

--- Mr. J. G. Reddy, Advocate for the Petitioner. None for the Respondents.

--- CORAM : V. M. KANADE AND MRS.SWAPNA JOSHI,JJ.

DATE : 04th OCTOBER, 2016 P.C. :

The Application is made by the learned counsel appearing for the Petitioner for speaking to the minutes of the order dated 06.09.2016.

It is submitted that in the first paragraph on the second line of the order dated 06.09.2016 it is wrongly mentioned that "We find that on the last date also, the same Advocate had taken time on the same ground." It is submitted that in fact on the earlier date i.e. on 29.08.2016, the affidavit Borey 1/2

spb/ 7conp81-13.odt in reply was filed by the Respondents and, therefore, time was taken by the Petitioner.

Accordingly, to that extent the order dated 06.09.2016 stands modified.

(MRS.SWAPNA JOSHI,J.) (V. M. KANADE,J.) .....

Borey 2/2