Mascots Infra Llp And 4 ORS v. Balaji Construction Company
911-CARBPL.1113.2019.doc Tauseef
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION PETITION NO.1113 OF 2019 Mascots Infra LLP & Ors.
...Petitioners
V/S.
Balaji Construction Company
...Respondent
Ms. Shweta Sharma for Petitioners.
M.J. Bhatt for Respondent.
CORAM : G.S. KULKARNI, J.
Date :
26th SEPTEMBER 2019.
P.C. :
1.
Learned counsel for the respondent would be correct in his contention that construction agreement is made and entered at Thane. This court has no jurisdiction to entertain this petition under Section 9 of the Arbitration and Conciliation Act, 1996. Accordingly, the petition is disposed of with liberty to the petitioner to move an appropriate Court. All contentions are recorded.
(G.S. KULKARNI, J.) Pg 1 of 1