IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO.1178 OF 2015 Nav Maharashtra Nagar Sahakari .Petitioners Grihnirman Sanstha And Ors.

v/s.

Maharashtra Housing And .Respondents Development Authority And Ors.

Mr.S.U.Kamdar Senior Counsel a/w Ms Jasmin Sheth & Mr.Karan Dua i/b. Wadia Ghandy & Co., Advocate, for the Petitioners Ms Aparna Murlidharan a/w. Mr.Aniket Poojary i/b. Mr.P.G.Lad, Advocate, for the Respondent Nos.1 & 2 Ms K.H.Mastakar, Advocate, for the Respondent No.3 - MCGM

CORAM

:

A.A.SAYED, J.

DATE :

09.07.2015 P.C.

.

Learned Senior counsel for the petitioners states that the representation of the petitioners for extension of time to vacate the transit accommodation is pending with the Vice President and Chief Executive Officer, MHADA. Learned Senior counsel further states

that in the entire scheme consisting of several societies, 2360 slum dwellers have been eligible for alternate accommodation and 2100 slum dwellers have already been shifted to the permanent alternate accommodation and only 260 slum dwellers are left to be rehabilitated. Learned Senior counsel states that only 2 buildings are left to be constructed and the construction is in progress and the same would be completed by end of the year 2016.

2.

Learned counsel for the MHADA confirms the representation of the petitioners is pending with VP & CEO, MHADA. She states that the representation will be considered and decided after hearing the petitioners and the Corporation.

3.

In the circumstances, in my view, no purpose would be served in keeping the Writ

Petition pending. Until the representation is decided, no coercive steps shall be taken by MHADA and Corporation. In the event, any adverse order is passed against the petitioners, the same shall not be implemented for a period of three weeks from the date of communication of the decision to the petitioners.

4.

The Petition is disposed of in the aforesaid terms.