906 ARBPL 1261 OF 2019 vks

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION ARBITRATION PETITION (L) NO.1261 OF 2019 Buncon Engineers & Infrastructure Pvt. Ltd.

...

Petitioner V/s.

Parle Gurudeo Co-op Housing Society Ltd.

...

Respondent Mr. Ritesh K. Jain, for the Petitioner.

Mr. A. D. Bagwe i/by Mulla & Mulla Craigie Blunt & Caroe, for respondent.

CORAM : G. S. KULKARNI, J.

DATE : 17th October, 2019.

P.C. :

1] This is a petition filed under Section 29A of the Arbitration and Conciliation Act, 1996 whereby the petitioner has prayed for extension of the mandate of the arbitral tribunal to complete the arbitral proceedings and publish an award. It is submitted that final arguments are concluded. The claimant's rejoinder argument would now be heard by the arbitral tribunal.

1/2

906 ARBPL 1261 OF 2019 2] Having perused the averments in the petition, the mandate of the arbitral tribunal to conclude the arbitral proceedings and publish an award is extended for a period of six months from 31st October, 2019. Ordered accordingly.

3] Disposed of. No costs.

[G. S. KULKARNI, J.] 2/2