← Library
Bombay High CourtCARBP/1395/2019disposed off

Prashant K. Doshi v. Orchid Builtcon Pvt. Ltd.

2019-10-22Hon'Ble Shri Justice G. S. Kulkarni1 pages

1 903-carbpl 1272-19 psv

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL ARBITRATION PETITION (L.) NO.1272 OF 2019 Prashant K. Doshi ..Petitioner Vs.

M/s.Orchid Builtcon Pvt. Ltd.

..Respondent ----- Mr.Atul Umekar i/b. M/s.Utangale & Co. for Petitioner. Mr.Yogesh Rane i/b. Mr.Harshad Rajeshirke for Respondent. ----- CORAM : G.S. KULKARNI, J.

DATE : 22nd OCTOBER, 2019 P.C.:

This is a petition filed under Section 29A of the Arbitration and Conciliation Act, 1996 whereby the petitioner has prayed for extension of time for a further period of six months, to enable the arbitral tribunal to complete the arbitral proceedings and publish an award. It is submitted that the final arguments are in progress. 2.

Having perused the averments in the petition, the mandate of the arbitral tribunal to conclude the arbitral proceedings and publish an award is required to be extended for a period of 3 months from today. Ordered accordingly.

3.

Disposed of. No costs.

[G.S. KULKARNI, J.]