Lauren Constructors Pvt Ltd v. Godawari Green Energy Ltd
1 905-carbpl 1275-19 pvr
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL ARBITRATION PETITION (L.) NO.1275 OF 2019 Lauren Constructors Private Ltd.
..Petitioner Vs.
Godawari Green Energy Limited ..Respondent ----- Ms.Sherna Doongaji with Ms.Ashrita Gulati i/b. AZB & Partners for Petitioner.
Ms.Salonee Kulkarni i/b. Shardul Amarchand Mangaldas & Co. for Respondent.
----- CORAM : G.S. KULKARNI, J.
DATE : 22nd OCTOBER, 2019 P.C.:
This is a petition filed under Section 29A of the Arbitration and Conciliation Act, 1996 whereby the petitioner has prayed for extension of time for a period of three months, to enable the arbitral tribunal to complete the arbitral proceedings and publish an award. It is informed that the arbitral tribunal is now proceeding to publish an award.
2.
Having perused the averments in the petition, the mandate of the arbitral tribunal to conclude the arbitral proceedings and publish an award is required to be extended. Accordingly, the mandate of the arbitral tribunal is extended for three months. The arbitral tribunal shall make an endeavour to conclude the arbitral proceedings. 3.
Disposed of. No costs.
[G.S. KULKARNI, J.]