Kranti Nagar Sra Chs (Prop.) v. Slum Rehabilitation Authority And 7 ORS
Chittewan 1/2
902. WPL 3578-18.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION (L) NO.3578 OF 2018 Kranti Nagar SRA CHS (Prop.) ...
Petitioner
Versus
Slum Rehabilitation Authority And Others ...
Respondents ALONG WITH WRIT PETITION (L) NO.4001 OF 2018 Sai Siddhi Realtors LLP ...
Petitioner
Versus
Slum Rehabilitation Authority And Others ...
Respondents .....
Mr. Mayur Khandeparkar I/b Mr. Hassan Ullah Khan for the Petitioner in Writ Petition (L) No.3578 of 2018.
Mr. G.S. Godbole I/b Ms. Jaswandi Khatu for the Petitioner in Writ Petition No.4001 of 2018.
Mr. Vijay Patil for Respondent Nos.1 and 2.
Mr. Cherag Balsara a/w Mr. Suraj Iyer I/b Ganesh & Co. for Respondent No.3.
Mr. Prasad Dhakephalkar, Senior Advocate a/w Mr. Farid Karachiwala, Ms. Sneh Parekh I/b M/s J. Sagar Associates for Respondent No.5. Ms. Pooja Yadav for Respondent No.8-MCGM.
.....
CORAM : S.C. GUPTE, J.
DATE : 14 MARCH 2019 P. C. :
.
After the matter is heard at some length, it is agreed between learned Counsel for the parties that the impugned order of the Apex Grievance Redressal Committee dated 17 September 2018, may be set
Chittewan 2/2
902. WPL 3578-18.doc aside, by consent. It is submitted that the Competent Authority (CA) may prepare and finalize a new Annexure-II in accordance with the order passed by the Chief Executive Officer (CEO), Slum Rehabilitation Authority (SRA) on 15 June 2016. It is agreed that the new developer will be appointed after finalization of eligibility of the slum dwellers in accordance with law. CA shall complete the exercise concerning the new Annexure II within a period of six weeks from today.
(S.C. GUPTE, J.)