← Library
Bombay High CourtCARBP/1572/2019disposed off

Balaji Motion Pictures Ltd v. Maruti International And 2 ORS

2019-12-12Hon'Ble Shri Justice G.S. Patel1 pages

934-CARBPL1507-19-I.DOC Shephali

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMM ARBITRATION PETITION (L) NO. 1507 OF 2019 Balaji Motion Pictures Ltd

...Petitioner

Versus

Maruti International & Ors

...Respondents

Mr Amogh Joshi, i/b Bharucha & Partners, for the Petitioner.

CORAM:

G.S. PATEL, J.

DATED:

12th December 2019 PC:- 1.

This is a Petition under Section 29-A of the Arbitration and Conciliation Act 1996. Mr Naushad Engineer was appointed as an Arbitrator on 4th May 2017. He entered upon the reference to his arbitration on 16th June 2017. The matter has progressed to the stage of evidence. Several witnesses have been cross-examined. It is only the evidence of the Respondent in arbitration that is yet to be concluded, after which the final hearing will be taken up. 2.

Time is extended till 3rd July 2020.

3.

The Petition is disposed of accordingly. There will be no order as to costs.

(G. S. PATEL, J) 12th December 2019