ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 757 OF 2019 IN APPEAL (L) NO. 537 OF 2019 Kanchan V.

Mayekar Kanchan V.

Mayekar Date: 2021.03.16 10:52:33 +0530 ALONGWITH INTERIM APPLICATION NO. 759 OF 2019 IN APPEAL (L) NO. 537 OF 2019 ALONGWITH APPEAL (L) NO. 537 OF 2019 Union of India ..... Applicant

IN THE MATTER BETWEEN

Union of India ..... Appellant

VERSUS

M/s. Vaman Prestressing Co. Pvt. Ltd. & Anr.

..... Respondents Mr.Chetan C.Agrawal for the Applicant/Appellant. None for the Respondents.

CORAM: R. D. DHANUKA AND V. G.BISHT, JJ.

DATE : 15th MARCH, 2021 P.C. :- Appeal (L) No. 537 of 2019 not on board. Taken on board. 2.

There is delay of 267 days in filing appeal admittedly. The appeal is barred by law of limitation. Interim Application No. 759 of

KVM 2/2 40 - IA 757 OF 2019.doc 2019 is accordingly dismissed.

3.

In view of the dismissal of the Interim Application No. 759 of 2019, Appeal (L) No.537 of 2019 is also dismissed. 4.

In view of the dismissal of the Appeal (L) No.537 of 2019, Interim Application No. 757 of 2019 for stay is also dismissed. No order as to costs.

[V.G.BISHT, J.] [R. D. DHANUKA, J.]